"Mainly down to street configuration." That was the explanation the applicant's representative gave the Planning Commission on Oct. 8, 2026, according to The Lexington Times. He was asking to postpone Andover Commons, Anderson Communities' 1,240-unit proposal at 4200 Todds Road, for the third time since late August.
Andover Commons is the largest housing proposal filed so far in the land Lexington added to its Urban Service Boundary in 2023. A three-year-old boundary decision is still negotiating where its streets go. If you are comparing Lexington with the counties around it, that fact matters more than any median price. The expansion area is real land with real plans, and it adds nothing to the supply you will be shopping against this winter or next.
Land was never the constraint the expansion removed
The Urban County Council approved the boundary change in June 2023. It added roughly 2,800 acres across five areas. The Planning Commission then adopted an Urban Growth Master Plan as part of Imagine Lexington 2045 at its October 2024 hearing. That plan sets the rules for how the new land must be laid out.
Those rules are where the time goes. The city's pending zoning-code update would set expansion-area standards for housing mix, buffers, transit and walkable shops, according to the Imagine Lexington zoning update page. Every proposal has to show that it meets the plan. Planning staff have repeatedly flagged the same kinds of gaps: street networks, block sizes, connectivity and traffic studies.
Before any of it can be built, someone has to pay for the roads and sewers that make the land usable. City staff estimated full-buildout infrastructure costs across all five areas at about $569 million, a figure CivicLex attributes to Partners for Economic Solutions.
Three proposals, none approved yet
The Lexington Times has tracked each case through its planning-filing reports, including the Aug. 31 roundup on Andover Commons, the Sept. 21 roundup on Ball Homes and OK Gentry, and the Sept. 28 update on the postponements. These are the residential rezoning cases in the expansion area as of mid-October 2026:
| Proposal | Location | What's proposed | Where it stood in mid-October 2026 |
|---|---|---|---|
| Andover Commons, Anderson Communities | 4200 Todds Road | 1,240 units on 123.13 net acres plus a 65,141-square-foot town center | Postponed Aug. 27, Sept. 24 and Oct. 8; docketed for Oct. 22 |
| Ball Homes | 5085 Athens Boonesboro Road | 560 homes on 37.15 net acres | Postponed Sept. 24; docketed for Oct. 22 |
| OK Gentry LLC | Athens Boonesboro Road | 434 apartments in eight buildings, with retail, hotel and office space | Postponed Sept. 24; set for Nov. 19 |
The staff objections are specific. On the Ball Homes case, The Lexington Times reported that staff raised master-plan compliance, street length, a missing traffic analysis and the need for a second fire-service access. On OK Gentry, staff pointed to a missing I-75 service road and an incomplete traffic study.
The Oct. 22 docket was heavy. It held Andover, Ball Homes and the Urban Growth Master Plan implementation text amendment, which carries the code standards these projects are being measured against. Even an approval at that hearing only settles zoning. Streets, sewer lines, permits and construction still have to follow before anyone closes on a house.
What the first homes will look like
Andover Commons shows what kind of supply the expansion area is designed to produce. Of its 1,240 proposed units, 241 are detached houses. The other units break down as follows:
- 195 townhouses
- 642 apartments
- 74 flats
- 26 carriage apartments
- 62 senior cottages
Detached houses make up about one in five units in that plan. That fits a master plan built around housing mix and walkable centers. For the buyer who pictures the expansion area as a future source of new detached homes with a Fayette County address, it means fewer of those homes than the acreage suggests, and a later arrival.
The bill for roads and sewers now has a mechanism
The money question moved forward this fall. On Sept. 10, 2026, the Urban County Council gave final approval to a "privilege fee" ordinance, enacted as O-088-2026, after a first reading on Aug. 27.
As CivicLex explained when the proposal left committee in June, developers who build shared infrastructure first get reimbursed by later developers who benefit from it, with the city acting as the middleman. Staff estimated that about $345 million of the roughly $569 million total could be recovered this way.
The enacted text works like this:
- Each shared project's documented cost is divided among the properties that benefit, by acreage. The project agreement sets the exact allocation.
- The developer who builds the infrastructure can charge an administrative fee of up to 5% of documented construction cost. LFUCG can add its own administrative fee of up to 0.5% of project cost.
- Simple interest runs at the 10-year Treasury yield plus 1%. It starts accruing after 30 days and lasts no more than 20 years.
The ordinance doesn't set a flat dollar fee per home. What it does is turn a road or sewer line into a shared cost with interest attached. Whichever builder develops land later inherits that cost before setting a price. The ordinance settles who pays first, and the roads and sewers still have to be designed and built before any lot is ready.
Why the timeline runs in years
Local business groups put a number on the wait. In February 2026, Commerce Lexington joined the Building Industry Association and Lexington For Everyone in the "30 by 30" housing campaign. Their statement said that, based on past experience, homebuilding in the expansion area would take five to seven years to begin. The same statement said Lexington is building about 600 new homes a year, roughly a third of its pace before the Great Recession.
The campaign also cites a need for 22,000 units right now, 14,000 rental and 8,000 single-family, rising past 30,000 by 2030, as LEX18 reported. Compare 600 homes a year with that figure and even fast approvals this fall would not change what is on the market in 2027.
What Fayette County's numbers look like while it waits
The latest county figures from Bluegrass REALTORS, covering August 2026, fit a market without much new supply coming in. Fayette County's median sale price was $362,500 in August 2026, up 3% from $353,000 in August 2025. Sales fell 11%, from 373 to 331. Fewer homes sold, and the median still rose.
The wider region moved differently. In August 2026, inventory across the association's 38-county region reached 4,578 homes, up 12% from a year earlier. Months of inventory rose to 3.6 from 3.0. Regional new-construction sales reached 124 that month, the highest August count since 2008, with the average 30-year mortgage rate at 6.67%. None of those new homes came from Lexington's expansion acreage, because nothing there had been approved.
Neighboring counties posted their own August 2026 results:
- Jessamine: $327,000 median, down 9%, on 72 sales, up 14%
- Scott: $355,000 median on 77 sales, down 20%
- Woodford: $380,000 median on 42 sales, up 62%
- Franklin: $265,000 median on 51 sales
For a buyer, this is where the expansion story pays off. If you want a newer home close to Lexington within the next year or two, you'll be comparing resale homes inside Fayette County with whatever is available in the surrounding counties. A plan on Todds Road or Athens Boonesboro Road won't be one of your options yet. A home inside the existing boundary benefits from that same scarcity when it comes time to sell.
FAQ
Can I buy a home in the 2023 expansion area today? As of mid-October 2026, none of the three reported residential rezonings in the expansion area had final approval. Zoning has to come before infrastructure, permits and construction.
Did the Oct. 22 hearing change the timeline? That hearing could settle zoning for Andover Commons or Ball Homes, along with the master plan's code standards. Streets, sewers and construction would still follow, and the OK Gentry case was set for Nov. 19.
Do buyers pay the privilege fee directly? The ordinance divides infrastructure costs among benefiting properties by acreage through project agreements between developers and the city. It doesn't set a per-home fee.
Is White Farm on Richmond Road part of the expansion? The Planning Commission approved White Farm's development plan for 114 townhomes and 480 multifamily units at 3515 Richmond Road on Oct. 8, 2026. Its approval is separate from the three expansion-area rezoning cases above.
If you're deciding between a resale home in Fayette County and new construction in a neighboring county, I can lay out the current options side by side and keep you posted as the expansion-area cases go back to the Planning Commission. Trey McCallie is here when you're ready. Let's Connect.